2nd Dug Hill Road Urbanization

Share 2nd Dug Hill Road Urbanization on Facebook Share 2nd Dug Hill Road Urbanization on Twitter Share 2nd Dug Hill Road Urbanization on Linkedin Email 2nd Dug Hill Road Urbanization link

Project overview

The 2nd Dug Hill Road urbanization project includes the installation of:

  • A new multi-use pathway separated from the road with a boulevard

  • A sidewalk on the west side, separated by a grassed boulevard

Image: Design rendering of new multi-use pathway and sidewalk

The new multi-use pathway will be installed on 2nd Dug Hill from Highway 2 south for approximately 1.6 km and will connect with additional trails being installed along 2nd Dug Hill Road as part of the Trenton West End Trunk Sewer Project.

Construction for the permanent multi-use pathway, originally scheduled to be installed in the summer and fall of 2025, has been delayed to spring/summer 2026. The project start date has been moved due to a delivery delay for a critical pipe for the 2nd Dug Hill Road stormwater pond, which is required to be installed prior to road work beginning.

Until the permanent multi-use pathway is installed, a temporary 1.5m asphalt millings pathway will be constructed from Highway 2 to Appledene Drive (see Figure 1 below) along the east side of 2nd Dug Hill Road. The temporary pathway installation is scheduled for November/December 2025 construction.


Image: Temporary sidewalk location

Project status and updates

The 2nd Dug Hill Road urbanization project was tendered in October 2025. Ten bids were received. The lowest five bids are:

  1. Behan Construction Limited: $4,182,799.62

  2. QBT Excavating Services Ltd.: $4,446,569.85

  3. Dekeyser Excavating Ltd.: $4,691,024.14

  4. Fidelity Engineering & Construction Inc.: $4,788,000.00

  5. Cobourg Development Services Ltd.: $4,864,163.00

The project is anticipated to be awarded in mid-November 2025.

Enbridge and gas relocations will occur in October and November 2025, and the installation of the temporary asphalt millings pathway is scheduled for November and December 2025.

Project timeline

  • Fall 2024: Public information centre #1 and community consultation

  • June 2025: Completion of detailed design and public information centre #2

  • September-October 2025: Project tendered

  • November 2025: Project tender award

  • November/December 2025: Installation of temporary asphalt millings pathway

  • Spring/summer 2026: First phase of construction for the permanent multi-use pathway

  • Summer 2026/2027: Final phase of construction (pending completion of trunk sewer main)


Project overview

The 2nd Dug Hill Road urbanization project includes the installation of:

  • A new multi-use pathway separated from the road with a boulevard

  • A sidewalk on the west side, separated by a grassed boulevard

Image: Design rendering of new multi-use pathway and sidewalk

The new multi-use pathway will be installed on 2nd Dug Hill from Highway 2 south for approximately 1.6 km and will connect with additional trails being installed along 2nd Dug Hill Road as part of the Trenton West End Trunk Sewer Project.

Construction for the permanent multi-use pathway, originally scheduled to be installed in the summer and fall of 2025, has been delayed to spring/summer 2026. The project start date has been moved due to a delivery delay for a critical pipe for the 2nd Dug Hill Road stormwater pond, which is required to be installed prior to road work beginning.

Until the permanent multi-use pathway is installed, a temporary 1.5m asphalt millings pathway will be constructed from Highway 2 to Appledene Drive (see Figure 1 below) along the east side of 2nd Dug Hill Road. The temporary pathway installation is scheduled for November/December 2025 construction.


Image: Temporary sidewalk location

Project status and updates

The 2nd Dug Hill Road urbanization project was tendered in October 2025. Ten bids were received. The lowest five bids are:

  1. Behan Construction Limited: $4,182,799.62

  2. QBT Excavating Services Ltd.: $4,446,569.85

  3. Dekeyser Excavating Ltd.: $4,691,024.14

  4. Fidelity Engineering & Construction Inc.: $4,788,000.00

  5. Cobourg Development Services Ltd.: $4,864,163.00

The project is anticipated to be awarded in mid-November 2025.

Enbridge and gas relocations will occur in October and November 2025, and the installation of the temporary asphalt millings pathway is scheduled for November and December 2025.

Project timeline

  • Fall 2024: Public information centre #1 and community consultation

  • June 2025: Completion of detailed design and public information centre #2

  • September-October 2025: Project tendered

  • November 2025: Project tender award

  • November/December 2025: Installation of temporary asphalt millings pathway

  • Spring/summer 2026: First phase of construction for the permanent multi-use pathway

  • Summer 2026/2027: Final phase of construction (pending completion of trunk sewer main)


Page last updated: 05 Nov 2025, 06:51 PM