2nd Dug Hill Road urbanization

Share 2nd Dug Hill Road urbanization on Facebook Share 2nd Dug Hill Road urbanization on Twitter Share 2nd Dug Hill Road urbanization on Linkedin Email 2nd Dug Hill Road urbanization link

2nd Dug Hill Road closure: Highway 2 to Appledene Drive beginning April 13

2nd Dug Hill Road will be closed beginning April 13 from Highway 2 south to Appledene Drive while construction begins on the 2nd Dug Hill Road urbanization project. Construction closures as part of this project will last into fall 2026. During construction, several temporary closures and detour routes will be in effect. Updates will be provided throughout the project.

Learn more about the closure and detour route »

Project overview

The 2nd Dug Hill Road urbanization project includes the installation of:

  • A new multi-use pathway separated from the road with a boulevard

  • A sidewalk on the west side, separated by a grassed boulevard

Image: Design rendering of new multi-use pathway and sidewalk

The new multi-use pathway will be installed on 2nd Dug Hill from Highway 2 south for approximately 1.6 km and will connect with additional trails being installed along 2nd Dug Hill Road as part of the Trenton West End Trunk Sewer Project.

Construction on the permanent multi-use pathway, sidewalk and road reconstruction will begin this spring.

Until the permanent multi-use pathway is installed, a temporary 1.5m asphalt millings pathway is available from Highway 2 to Appledene Drive (see Figure 1 below) along the east side of 2nd Dug Hill Road. The temporary pathway was installed late 2025.

Image: Temporary sidewalk location

Project tender and award

The 2nd Dug Hill Road urbanization project was tendered in October 2025. Ten bids were received. The lowest five bids are:

  1. Behan Construction Limited: $4,182,799.62

  2. QBT Excavating Services Ltd.: $4,446,569.85

  3. Dekeyser Excavating Ltd.: $4,691,024.14

  4. Fidelity Engineering & Construction Inc.: $4,788,000.00

  5. Cobourg Development Services Ltd.: $4,864,163.00

The project was awarded to Behan Construction Limited in mid-November 2025.

Project timeline

  • Fall 2024: Public information centre #1 and community consultation

  • June 2025: Completion of detailed design and public information centre #2

  • September-October 2025: Project tendered

  • November 2025: Project tender award

  • October/November 2025: Enbridge and gas relocations

  • November/December 2025: Installation of temporary asphalt millings pathway

  • Spring/summer 2026: First phase of construction for the permanent multi-use pathway

  • Summer 2026/2027: Final phase of construction (pending completion of trunk sewer main)

Project updates and service impacts


2nd Dug Hill Road closure: Highway 2 to Appledene Drive beginning April 13

2nd Dug Hill Road will be closed beginning April 13 from Highway 2 south to Appledene Drive while construction begins on the 2nd Dug Hill Road urbanization project. Construction closures as part of this project will last into fall 2026. During construction, several temporary closures and detour routes will be in effect. Updates will be provided throughout the project.

Learn more about the closure and detour route »

Project overview

The 2nd Dug Hill Road urbanization project includes the installation of:

  • A new multi-use pathway separated from the road with a boulevard

  • A sidewalk on the west side, separated by a grassed boulevard

Image: Design rendering of new multi-use pathway and sidewalk

The new multi-use pathway will be installed on 2nd Dug Hill from Highway 2 south for approximately 1.6 km and will connect with additional trails being installed along 2nd Dug Hill Road as part of the Trenton West End Trunk Sewer Project.

Construction on the permanent multi-use pathway, sidewalk and road reconstruction will begin this spring.

Until the permanent multi-use pathway is installed, a temporary 1.5m asphalt millings pathway is available from Highway 2 to Appledene Drive (see Figure 1 below) along the east side of 2nd Dug Hill Road. The temporary pathway was installed late 2025.

Image: Temporary sidewalk location

Project tender and award

The 2nd Dug Hill Road urbanization project was tendered in October 2025. Ten bids were received. The lowest five bids are:

  1. Behan Construction Limited: $4,182,799.62

  2. QBT Excavating Services Ltd.: $4,446,569.85

  3. Dekeyser Excavating Ltd.: $4,691,024.14

  4. Fidelity Engineering & Construction Inc.: $4,788,000.00

  5. Cobourg Development Services Ltd.: $4,864,163.00

The project was awarded to Behan Construction Limited in mid-November 2025.

Project timeline

  • Fall 2024: Public information centre #1 and community consultation

  • June 2025: Completion of detailed design and public information centre #2

  • September-October 2025: Project tendered

  • November 2025: Project tender award

  • October/November 2025: Enbridge and gas relocations

  • November/December 2025: Installation of temporary asphalt millings pathway

  • Spring/summer 2026: First phase of construction for the permanent multi-use pathway

  • Summer 2026/2027: Final phase of construction (pending completion of trunk sewer main)

Project updates and service impacts


Page last updated: 10 Apr 2026, 10:22 AM