We use cookies to ensure our site functions properly and to store limited information about your usage. You may give or withdraw consent at any time. To find out more, read our privacy policy and cookie policy.
Manage Cookies
A cookie is information stored on your computer by a website you visit. Cookies often store your settings for a website, such as your preferred language or location. This allows the site to present you with information customized to fit your needs. As per the GDPR law, companies need to get your explicit approval to collect your data. Some of these cookies are ‘strictly necessary’ to provide the basic functions of the website and can not be turned off, while others if present, have the option of being turned off. Learn more about our Privacy and Cookie policies. These can be managed also from our cookie policy page.
Strictly necessary cookies(always on):
Necessary for enabling core functionality. The website cannot function properly without these cookies. This cannot be turned off. e.g. Sign in, Language
Analytics cookies:
Analytical cookies help us to analyse user behaviour, mainly to see if the users are able to find and act on things that they are looking for. They allow us to recognise and count the number of visitors and to see how visitors move around our website when they are using it. Tools used: Google Analytics
Share North Trent Street and Huffman Road pipe upsizing on FacebookShare North Trent Street and Huffman Road pipe upsizing on X (formerly Twitter)Share North Trent Street and Huffman Road pipe upsizing on LinkedinEmail North Trent Street and Huffman Road pipe upsizing link
North Trent Street in Frankford will undergo significant construction from June 2026 until late Fall 2026.
Identified in the Water and Wastewater Master Plan, this project includes the upsizing of the existing wastewater pipe at the intersection of North Trent Street and Huffman Road to allow for future development growth in the northwest area of Frankford.
About the project
This project includes:
Road reconstruction, including new asphalt and curb
Installation of a second sanitary forcemain
Upsizing the underground sanitary gravity sewer
Project area
Updated Sept. 25, 2026 - Starting Sept. 28, 2026, the construction area on North Trent Street in Frankford will expand north to include the full intersection of Huffman Road and North Trent Street for the next stage of work. The area of work continues south to Adelaide Street, where construction began earlier this summer to install a second sanitary force main and an updated gravity sewer.
Updated detour routes connecting North Trent Street to Huffman Road via Rosewood subdivision will be posted while work continues in the intersection. Please follow posted detour signs.
Access will be maintained at the construction area for emergency vehicles and local traffic only.
Work is progressing as scheduled. Curb, sidewalk and asphalt are being installed in parts of the construction zone. The full project is expected to be completed in late fall 2026.
Learn more and stay up to date on the North Trent Street and Huffman Road pipe upsizing project at quintewest.ca/NorthTrent.
Stay up to date
Information on project milestones and updates will be shared on this page and on the City's social media channels.
North Trent Street in Frankford will undergo significant construction from June 2026 until late Fall 2026.
Identified in the Water and Wastewater Master Plan, this project includes the upsizing of the existing wastewater pipe at the intersection of North Trent Street and Huffman Road to allow for future development growth in the northwest area of Frankford.
About the project
This project includes:
Road reconstruction, including new asphalt and curb
Installation of a second sanitary forcemain
Upsizing the underground sanitary gravity sewer
Project area
Updated Sept. 25, 2026 - Starting Sept. 28, 2026, the construction area on North Trent Street in Frankford will expand north to include the full intersection of Huffman Road and North Trent Street for the next stage of work. The area of work continues south to Adelaide Street, where construction began earlier this summer to install a second sanitary force main and an updated gravity sewer.
Updated detour routes connecting North Trent Street to Huffman Road via Rosewood subdivision will be posted while work continues in the intersection. Please follow posted detour signs.
Access will be maintained at the construction area for emergency vehicles and local traffic only.
Work is progressing as scheduled. Curb, sidewalk and asphalt are being installed in parts of the construction zone. The full project is expected to be completed in late fall 2026.
Learn more and stay up to date on the North Trent Street and Huffman Road pipe upsizing project at quintewest.ca/NorthTrent.
Stay up to date
Information on project milestones and updates will be shared on this page and on the City's social media channels.
Page last updated: 25 Sep 2026, 06:29 AM
June 2026
North Trent Street and Huffman Road pipe upsizing has finished this stage
Affected residents are notified of upcoming construction and detour routes.
July 13, 2026 - Construction begins
North Trent Street and Huffman Road pipe upsizing has finished this stage
Contractor crews and equipment are mobilized on North Trent Street and begin work July 13.
North Trent Street will be closed between Concession Road and Adelaide Street. Traffic will be detoured to King Drive during this phase of construction.
August 11 to late September - New detour routes in effect
North Trent Street and Huffman Road pipe upsizing has finished this stage
Construction is progressing well on North Trent Street, Frankford.
NEW: Detour routes have been updated starting Aug. 11 ending in October 2026.
North Trent Street will be closed between Huffman Road and Adelaide Street. Traffic will be detoured to Pitchers Road via Huffman Road and County Road 5 (Mill Street) during this phase of construction.
September 28 into October 2026
North Trent Street and Huffman Road pipe upsizing is currently at this stage
Starting Monday, Sept. 28, traffic will be routed through Rosewood subdivision to access Huffman Road.
Roadside signage will be in place to mark the detour route.
The area of construction will now include the intersection of Huffman Avenue and North Trent Street.
Late Fall 2026
this is an upcoming stage for North Trent Street and Huffman Road pipe upsizing
Work is scheduled to be completed late into the Fall of 2026.