November 2024

Public information centre #1 and community consultation

A public information centre (PIC) was held on Nov. 14 from 4-7 p.m. at the Trenton Wesleyan Church to learn more about the project and receive feedback on the proposed design options.

June 2025

Completion of detailed design and public information centre #2

Public input was sought through a community survey on the preferred multi-use pathway design.

September → October 2025

Project tendered

Learn more about the next steps for the project at a Public Information Centre on June 17, 2925, from 4:30 - 7 p.m. at Trent Port Marina.

November 2025

Project tender awarded

November → December 2025

Installation of temporary asphalt millings pathway

April 01 → August 31 2026

First phase of construction for the permanent multi-use pathway